It’s been a while since I’ve given you a construction update, so here are some photos of the latest that’s going on in the vestibule. Currently, here’s what our construction team is focusing on:
· Most of November and December was spent underground — lots of work needed to be done regarding mechanical and electrical stuff before the slab was poured.
· The foundation has now been poured!
· We also did a lot of work while school was on break to run piping through the cafeteria in order to connect
the vestibule HVAC with our existing chiller and boiler systems.
· The next step is to start putting up the steel frame! This process has just begun!
Many thanks to our architect, parishioner Andrew Roche of Creative Design Solutions, for the great photos!